Perbandingan Produktivitas Tenaga Kerja Proyek Konstruksi Saat Jam Kerja Normal Dan Lembur Di Kota Padang

Construction projects have three targets that must be achieved, namely accuracy of cost, time and quality. These three targets are influenced by work productivity. However, in the implementation of construction projects there are often delays. So, contractors usually do various ways to catch up on p...

Full description

Saved in:
Bibliographic Details
Main Authors: Azdharizka Yunita, Benny Hidayat
Format: Article
Language:English
Published: Jurusan Teknik Sipil, Fakultas Teknik, Universitas Andalas 2024-09-01
Series:Jurnal Bangunan, Konstruksi & Desain
Subjects:
Online Access:https://jbkd.ft.unand.ac.id/index.php/jbkd/article/view/80
Tags: Add Tag
No Tags, Be the first to tag this record!
_version_ 1832594103197499392
author Azdharizka Yunita
Benny Hidayat
author_facet Azdharizka Yunita
Benny Hidayat
author_sort Azdharizka Yunita
collection DOAJ
description Construction projects have three targets that must be achieved, namely accuracy of cost, time and quality. These three targets are influenced by work productivity. However, in the implementation of construction projects there are often delays. So, contractors usually do various ways to catch up on project delays. One of the things that contractors do to speed up work is by adding working hours outside of regular working hours or overtime. When working during regular working hours, there will be different conditions during overtime, causing differences in productivity levels between the two. The amount of productivity produced is influenced by many factors. Factors, such as field conditions and supporting facilities, job skills, age, experience, and field management. This study was conducted using observation and questionnaire methods. The observation method is carried out by measuring the implementation of work during normal and overtime hours and recording activities. Questionnaires were distributed to workers to obtain factors that affect labor productivity. The results obtained were average productivity during normal hours of 2,018 m2/hour and overtime hours of 2,043 m2/hour. The average LUR value during normal working hours is 61.39% and overtime hours is 64.66%. In addition, factors that greatly influence are workers' wages, weather conditions, work area conditions, and lack of rest time.
format Article
id doaj-art-d204d007ba864126847c5e4b70dae8d7
institution Kabale University
issn 3021-7547
language English
publishDate 2024-09-01
publisher Jurusan Teknik Sipil, Fakultas Teknik, Universitas Andalas
record_format Article
series Jurnal Bangunan, Konstruksi & Desain
spelling doaj-art-d204d007ba864126847c5e4b70dae8d72025-01-20T05:25:06ZengJurusan Teknik Sipil, Fakultas Teknik, Universitas AndalasJurnal Bangunan, Konstruksi & Desain3021-75472024-09-012318019010.25077/jbkd.2.3.180-190.202480Perbandingan Produktivitas Tenaga Kerja Proyek Konstruksi Saat Jam Kerja Normal Dan Lembur Di Kota PadangAzdharizka Yunita0Benny Hidayat1Universitas AndalasUniversitas AndalasConstruction projects have three targets that must be achieved, namely accuracy of cost, time and quality. These three targets are influenced by work productivity. However, in the implementation of construction projects there are often delays. So, contractors usually do various ways to catch up on project delays. One of the things that contractors do to speed up work is by adding working hours outside of regular working hours or overtime. When working during regular working hours, there will be different conditions during overtime, causing differences in productivity levels between the two. The amount of productivity produced is influenced by many factors. Factors, such as field conditions and supporting facilities, job skills, age, experience, and field management. This study was conducted using observation and questionnaire methods. The observation method is carried out by measuring the implementation of work during normal and overtime hours and recording activities. Questionnaires were distributed to workers to obtain factors that affect labor productivity. The results obtained were average productivity during normal hours of 2,018 m2/hour and overtime hours of 2,043 m2/hour. The average LUR value during normal working hours is 61.39% and overtime hours is 64.66%. In addition, factors that greatly influence are workers' wages, weather conditions, work area conditions, and lack of rest time.https://jbkd.ft.unand.ac.id/index.php/jbkd/article/view/80produktivitastenaga kerjajam kerja normaljam kerja lembur
spellingShingle Azdharizka Yunita
Benny Hidayat
Perbandingan Produktivitas Tenaga Kerja Proyek Konstruksi Saat Jam Kerja Normal Dan Lembur Di Kota Padang
Jurnal Bangunan, Konstruksi & Desain
produktivitas
tenaga kerja
jam kerja normal
jam kerja lembur
title Perbandingan Produktivitas Tenaga Kerja Proyek Konstruksi Saat Jam Kerja Normal Dan Lembur Di Kota Padang
title_full Perbandingan Produktivitas Tenaga Kerja Proyek Konstruksi Saat Jam Kerja Normal Dan Lembur Di Kota Padang
title_fullStr Perbandingan Produktivitas Tenaga Kerja Proyek Konstruksi Saat Jam Kerja Normal Dan Lembur Di Kota Padang
title_full_unstemmed Perbandingan Produktivitas Tenaga Kerja Proyek Konstruksi Saat Jam Kerja Normal Dan Lembur Di Kota Padang
title_short Perbandingan Produktivitas Tenaga Kerja Proyek Konstruksi Saat Jam Kerja Normal Dan Lembur Di Kota Padang
title_sort perbandingan produktivitas tenaga kerja proyek konstruksi saat jam kerja normal dan lembur di kota padang
topic produktivitas
tenaga kerja
jam kerja normal
jam kerja lembur
url https://jbkd.ft.unand.ac.id/index.php/jbkd/article/view/80
work_keys_str_mv AT azdharizkayunita perbandinganproduktivitastenagakerjaproyekkonstruksisaatjamkerjanormaldanlemburdikotapadang
AT bennyhidayat perbandinganproduktivitastenagakerjaproyekkonstruksisaatjamkerjanormaldanlemburdikotapadang