Numerical Investigation into the Effects of Controlled Tunnel Blast on Dynamic Responses of the Transmission Tower
At present, the drill-and-blast method is still one of the main construction means in the road tunnel excavation process. When the tunnel penetrates underneath sensitive structures such as high-voltage transmission towers, the blasting and supporting parameters must be strictly controlled to ensure...
Saved in:
Main Authors: | Feng Wang, Gaohai Zhang, Wenwen Li, Hongwei Nie |
---|---|
Format: | Article |
Language: | English |
Published: |
Wiley
2023-01-01
|
Series: | Advances in Civil Engineering |
Online Access: | http://dx.doi.org/10.1155/2023/6021465 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Similar Items
-
Influence and the Control of Shield Tunneling on Ancient Tower Vibration
by: Xu Liang, et al.
Published: (2024-01-01) -
Optimization of VEDs for Vibration Control of Transmission Line Tower
by: Guoping Huang, et al.
Published: (2021-01-01) -
FE Simulation of Transmission Tower
by: Boshra Eltaly, et al.
Published: (2014-01-01) -
The Influence of Small Clear-Distance Tunnel Construction on Adjacent High-Voltage Transmission Tower Foundation
by: Aijun Yao, et al.
Published: (2023-01-01) -
Research on Dynamic Response of Shallow Buried Tunnel Lining Constructed by Drilling and Blasting Method
by: Bo Wu, et al.