Construction of J.P. Magufuli Extradosed Cable-Stayed Bridge (3.0 km) at Mwanza, Tanzania, near Kigongo / Busisi Ferry
The J.P. Magufuli extradosed bridge is currently under construction. This bridge crossing Lake Victoria has an overall length of 3,000 m and a deck width of 28.45 m to accommodate 4 lanes of 3.5 m wide carriageways of vehicular traffic, a shoulder of 2.5 m+2.5 m for emergency parking and vehicle bre...
Saved in:
| Main Author: | |
|---|---|
| Format: | Article |
| Language: | English |
| Published: |
Editorial Department of Progress in Prestress Technology, Tongji University
2025-06-01
|
| Series: | 预应力技术 |
| Subjects: | |
| Online Access: | https://ptmc.tongji.edu.cn/yyljs/article/pdf/202502005 |
| Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
| _version_ | 1849684158683545600 |
|---|---|
| author | Katelula Salum Kaswaga |
| author_facet | Katelula Salum Kaswaga |
| author_sort | Katelula Salum Kaswaga |
| collection | DOAJ |
| description | The J.P. Magufuli extradosed bridge is currently under construction. This bridge crossing Lake Victoria has an overall length of 3,000 m and a deck width of 28.45 m to accommodate 4 lanes of 3.5 m wide carriageways of vehicular traffic, a shoulder of 2.5 m+2.5 m for emergency parking and vehicle breakdown on each side, a 2.5 m+2.5 m footpath for pedestrians on each side, and a median of 2.45 m. The structural arrangement of the main bridge is 100 m+160 m + 160 m+100 m = 520 m, and the approach bridge prestressed concrete (PSC) beam bridge L = 2,480 m (including 31@40=1,240 m on each side). The superstructure is an extradosed bridge with an RCC deck with three RCC pylons 18.856 m in height. The girder heights at the mid-span and end-span are 5.4 m and 3.2 m, respectively. This paper discusses the construction aspects of the J.P. Magufuli bridge along with the details of a special traveling formwork (Form-Traveller) that is used to enable balanced cantilever construction, Pylons, PC House construction for the Pile Cap, and Deck Slab Partial Depth Panel for Deck Slab Construction. |
| format | Article |
| id | doaj-art-a22de9ef818c4c68afe6ac2c6d4a593c |
| institution | DOAJ |
| issn | 2521-9480 |
| language | English |
| publishDate | 2025-06-01 |
| publisher | Editorial Department of Progress in Prestress Technology, Tongji University |
| record_format | Article |
| series | 预应力技术 |
| spelling | doaj-art-a22de9ef818c4c68afe6ac2c6d4a593c2025-08-20T03:23:34ZengEditorial Department of Progress in Prestress Technology, Tongji University预应力技术2521-94802025-06-0132546810.59238/j.pt.2025.02.005Construction of J.P. Magufuli Extradosed Cable-Stayed Bridge (3.0 km) at Mwanza, Tanzania, near Kigongo / Busisi FerryKatelula Salum KaswagaThe J.P. Magufuli extradosed bridge is currently under construction. This bridge crossing Lake Victoria has an overall length of 3,000 m and a deck width of 28.45 m to accommodate 4 lanes of 3.5 m wide carriageways of vehicular traffic, a shoulder of 2.5 m+2.5 m for emergency parking and vehicle breakdown on each side, a 2.5 m+2.5 m footpath for pedestrians on each side, and a median of 2.45 m. The structural arrangement of the main bridge is 100 m+160 m + 160 m+100 m = 520 m, and the approach bridge prestressed concrete (PSC) beam bridge L = 2,480 m (including 31@40=1,240 m on each side). The superstructure is an extradosed bridge with an RCC deck with three RCC pylons 18.856 m in height. The girder heights at the mid-span and end-span are 5.4 m and 3.2 m, respectively. This paper discusses the construction aspects of the J.P. Magufuli bridge along with the details of a special traveling formwork (Form-Traveller) that is used to enable balanced cantilever construction, Pylons, PC House construction for the Pile Cap, and Deck Slab Partial Depth Panel for Deck Slab Construction.https://ptmc.tongji.edu.cn/yyljs/article/pdf/202502005 extradosed bridge cantilever construction travelling formwork climbing formwork deck slab panel pc house pile cap pylons |
| spellingShingle | Katelula Salum Kaswaga Construction of J.P. Magufuli Extradosed Cable-Stayed Bridge (3.0 km) at Mwanza, Tanzania, near Kigongo / Busisi Ferry 预应力技术 extradosed bridge cantilever construction travelling formwork climbing formwork deck slab panel pc house pile cap pylons |
| title | Construction of J.P. Magufuli Extradosed Cable-Stayed Bridge (3.0 km) at Mwanza, Tanzania, near Kigongo / Busisi Ferry |
| title_full | Construction of J.P. Magufuli Extradosed Cable-Stayed Bridge (3.0 km) at Mwanza, Tanzania, near Kigongo / Busisi Ferry |
| title_fullStr | Construction of J.P. Magufuli Extradosed Cable-Stayed Bridge (3.0 km) at Mwanza, Tanzania, near Kigongo / Busisi Ferry |
| title_full_unstemmed | Construction of J.P. Magufuli Extradosed Cable-Stayed Bridge (3.0 km) at Mwanza, Tanzania, near Kigongo / Busisi Ferry |
| title_short | Construction of J.P. Magufuli Extradosed Cable-Stayed Bridge (3.0 km) at Mwanza, Tanzania, near Kigongo / Busisi Ferry |
| title_sort | construction of j p magufuli extradosed cable stayed bridge 3 0 km at mwanza tanzania near kigongo busisi ferry |
| topic | extradosed bridge cantilever construction travelling formwork climbing formwork deck slab panel pc house pile cap pylons |
| url | https://ptmc.tongji.edu.cn/yyljs/article/pdf/202502005 |
| work_keys_str_mv | AT katelulasalumkaswaga constructionofjpmagufuliextradosedcablestayedbridge30kmatmwanzatanzanianearkigongobusisiferry |