Analysis on Deformation and Stress Characteristics of a Multibraced Pit-in-Pit Excavation in a Subway Transfer Station

As an important part of subway transfer station construction, pit-in-pit (PIP) excavation has always been a key object of monitoring and control. In this study, taking the PIP excavation project of Hefei metro line 4 and line 7 transfer station as the background, combined with on-site monitoring and...

Full description

Saved in:
Bibliographic Details
Main Authors: Xin Shi, Chuanxin Rong, Hua Cheng, Linzhao Cui, Bin Wang, Shicheng Sun
Format: Article
Language:English
Published: Wiley 2020-01-01
Series:Advances in Civil Engineering
Online Access:http://dx.doi.org/10.1155/2020/8844461
Tags: Add Tag
No Tags, Be the first to tag this record!
_version_ 1832550479712747520
author Xin Shi
Chuanxin Rong
Hua Cheng
Linzhao Cui
Bin Wang
Shicheng Sun
author_facet Xin Shi
Chuanxin Rong
Hua Cheng
Linzhao Cui
Bin Wang
Shicheng Sun
author_sort Xin Shi
collection DOAJ
description As an important part of subway transfer station construction, pit-in-pit (PIP) excavation has always been a key object of monitoring and control. In this study, taking the PIP excavation project of Hefei metro line 4 and line 7 transfer station as the background, combined with on-site monitoring and numerical simulation, the variation law of lateral wall displacement, ground surface settlement, and strut force during the PIP excavation were analyzed. The results showed that the maximum lateral deformation of the pile caused by the excavation of the external pit accounted for 80%–90% of the total deformation and the surface settlement accounted for 70% of the total settlement. The excavation of the inner pit only made the maximum lateral wall displacement of the outer pit and the surface settlement behind the wall increase slightly, the growth rate tended to zero, and the maximum lateral deformation depth was all above the excavation surface, which indicated that, for this project, the inner excavation had little effect on the outer pit retaining structure. In addition, the increased exposure time of the soil at the bottom of the pit and the presence of the corner effect will cause the further development of the structure displacement and the surface settlement. Based on strut force measurements, using the tributary area load distribution procedure, it was obtained that 0.3γHe was used as the upper limit index of strut force in the region, where γ is the weight of the soil and He is the excavation depth of the foundation pit. The research conclusions were helpful for the construction and sustainable development of the PIP project.
format Article
id doaj-art-407973cfe84c4630bb0b5b073214f18a
institution Kabale University
issn 1687-8086
1687-8094
language English
publishDate 2020-01-01
publisher Wiley
record_format Article
series Advances in Civil Engineering
spelling doaj-art-407973cfe84c4630bb0b5b073214f18a2025-02-03T06:06:32ZengWileyAdvances in Civil Engineering1687-80861687-80942020-01-01202010.1155/2020/88444618844461Analysis on Deformation and Stress Characteristics of a Multibraced Pit-in-Pit Excavation in a Subway Transfer StationXin Shi0Chuanxin Rong1Hua Cheng2Linzhao Cui3Bin Wang4Shicheng Sun5State Key Laboratory of Mining Response and Disaster Prevention and Control in Deep Coal Mine, Anhui University of Science and Technology, Huainan 232001, ChinaState Key Laboratory of Mining Response and Disaster Prevention and Control in Deep Coal Mine, Anhui University of Science and Technology, Huainan 232001, ChinaSchool of Civil Engineering and Architecture, Anhui University of Science and Technology, Huainan 232001, ChinaAnhui Water Resources Development Co., Ltd., Bengbu 233000, ChinaSchool of Civil Engineering and Architecture, Anhui University of Science and Technology, Huainan 232001, ChinaSchool of Civil Engineering and Architecture, Anhui University of Science and Technology, Huainan 232001, ChinaAs an important part of subway transfer station construction, pit-in-pit (PIP) excavation has always been a key object of monitoring and control. In this study, taking the PIP excavation project of Hefei metro line 4 and line 7 transfer station as the background, combined with on-site monitoring and numerical simulation, the variation law of lateral wall displacement, ground surface settlement, and strut force during the PIP excavation were analyzed. The results showed that the maximum lateral deformation of the pile caused by the excavation of the external pit accounted for 80%–90% of the total deformation and the surface settlement accounted for 70% of the total settlement. The excavation of the inner pit only made the maximum lateral wall displacement of the outer pit and the surface settlement behind the wall increase slightly, the growth rate tended to zero, and the maximum lateral deformation depth was all above the excavation surface, which indicated that, for this project, the inner excavation had little effect on the outer pit retaining structure. In addition, the increased exposure time of the soil at the bottom of the pit and the presence of the corner effect will cause the further development of the structure displacement and the surface settlement. Based on strut force measurements, using the tributary area load distribution procedure, it was obtained that 0.3γHe was used as the upper limit index of strut force in the region, where γ is the weight of the soil and He is the excavation depth of the foundation pit. The research conclusions were helpful for the construction and sustainable development of the PIP project.http://dx.doi.org/10.1155/2020/8844461
spellingShingle Xin Shi
Chuanxin Rong
Hua Cheng
Linzhao Cui
Bin Wang
Shicheng Sun
Analysis on Deformation and Stress Characteristics of a Multibraced Pit-in-Pit Excavation in a Subway Transfer Station
Advances in Civil Engineering
title Analysis on Deformation and Stress Characteristics of a Multibraced Pit-in-Pit Excavation in a Subway Transfer Station
title_full Analysis on Deformation and Stress Characteristics of a Multibraced Pit-in-Pit Excavation in a Subway Transfer Station
title_fullStr Analysis on Deformation and Stress Characteristics of a Multibraced Pit-in-Pit Excavation in a Subway Transfer Station
title_full_unstemmed Analysis on Deformation and Stress Characteristics of a Multibraced Pit-in-Pit Excavation in a Subway Transfer Station
title_short Analysis on Deformation and Stress Characteristics of a Multibraced Pit-in-Pit Excavation in a Subway Transfer Station
title_sort analysis on deformation and stress characteristics of a multibraced pit in pit excavation in a subway transfer station
url http://dx.doi.org/10.1155/2020/8844461
work_keys_str_mv AT xinshi analysisondeformationandstresscharacteristicsofamultibracedpitinpitexcavationinasubwaytransferstation
AT chuanxinrong analysisondeformationandstresscharacteristicsofamultibracedpitinpitexcavationinasubwaytransferstation
AT huacheng analysisondeformationandstresscharacteristicsofamultibracedpitinpitexcavationinasubwaytransferstation
AT linzhaocui analysisondeformationandstresscharacteristicsofamultibracedpitinpitexcavationinasubwaytransferstation
AT binwang analysisondeformationandstresscharacteristicsofamultibracedpitinpitexcavationinasubwaytransferstation
AT shichengsun analysisondeformationandstresscharacteristicsofamultibracedpitinpitexcavationinasubwaytransferstation