Collaborative planning of subcontractors using the Last Planner System: a case study on a gas subcontractor in repetitive housing projects
The efficient management of subcontractors turns into a challenge in contracts with fixed prices and short terms. Non-conformances due to poor deliverables are common, generating delays and cost overruns for all parties involved, especially for the main contractor. In addition, in recent years some...
Saved in:
Main Authors: | , , |
---|---|
Format: | Article |
Language: | English |
Published: |
Universidad Politécnica de Madrid
2024-03-01
|
Series: | Anales de Edificación |
Subjects: | |
Online Access: | https://polired.upm.es/index.php/anales_de_edificacion/article/view/5306 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
_version_ | 1832096732084699136 |
---|---|
author | Xavier Brioso Karla Delgado-Martínez Luis Bravo-Salomón |
author_facet | Xavier Brioso Karla Delgado-Martínez Luis Bravo-Salomón |
author_sort | Xavier Brioso |
collection | DOAJ |
description | The efficient management of subcontractors turns into a challenge in contracts with fixed prices and short terms. Non-conformances due to poor deliverables are common, generating delays and cost overruns for all parties involved, especially for the main contractor. In addition, in recent years some collaborative systems have appeared, such as the Last Planner System (LPS), which has proven to be very efficient in the generation of value and the optimization of resources. However, there is still little information about successful results in the management of subcontractors. The main objective of this study is to propose a method that adapts the LPS for the management of the subcontract of natural gas facilities in highly repetitive housing projects, as well as to apply it successfully. The methodology was applied to a massive multi-family low-cost housing project in the city of Lima, Peru, which was modeled by using BIM technology. The most frequent root causes of non-conformances were determined for the first buildings, and this information was used for the collaborative planning of the following buildings. This allowed to determine the optimal sectioning, Takt Time Planning, subcontractor restrictions, weekly and daily planning, and finally, the lessons learned from the implementation of the LPS for future projects, which can be adapted to other types of subcontracts |
format | Article |
id | doaj-art-2b5809a2a9d944a19ddb19de6442ff00 |
institution | Kabale University |
issn | 2444-1309 |
language | English |
publishDate | 2024-03-01 |
publisher | Universidad Politécnica de Madrid |
record_format | Article |
series | Anales de Edificación |
spelling | doaj-art-2b5809a2a9d944a19ddb19de6442ff002025-02-05T10:55:14ZengUniversidad Politécnica de MadridAnales de Edificación2444-13092024-03-0191263210.20868/ade.2024.53068223Collaborative planning of subcontractors using the Last Planner System: a case study on a gas subcontractor in repetitive housing projectsXavier Brioso0https://orcid.org/0000-0002-0174-0241Karla Delgado-Martínez1https://orcid.org/0009-0004-3627-0982Luis Bravo-Salomón2https://orcid.org/0000-0003-1476-9710Pontifical Catholic University of PeruPontifical Catholic University of PeruPontifical Catholic University of PeruThe efficient management of subcontractors turns into a challenge in contracts with fixed prices and short terms. Non-conformances due to poor deliverables are common, generating delays and cost overruns for all parties involved, especially for the main contractor. In addition, in recent years some collaborative systems have appeared, such as the Last Planner System (LPS), which has proven to be very efficient in the generation of value and the optimization of resources. However, there is still little information about successful results in the management of subcontractors. The main objective of this study is to propose a method that adapts the LPS for the management of the subcontract of natural gas facilities in highly repetitive housing projects, as well as to apply it successfully. The methodology was applied to a massive multi-family low-cost housing project in the city of Lima, Peru, which was modeled by using BIM technology. The most frequent root causes of non-conformances were determined for the first buildings, and this information was used for the collaborative planning of the following buildings. This allowed to determine the optimal sectioning, Takt Time Planning, subcontractor restrictions, weekly and daily planning, and finally, the lessons learned from the implementation of the LPS for future projects, which can be adapted to other types of subcontractshttps://polired.upm.es/index.php/anales_de_edificacion/article/view/5306last planner system; subcontractor management; gas facilities management; continuous improvement |
spellingShingle | Xavier Brioso Karla Delgado-Martínez Luis Bravo-Salomón Collaborative planning of subcontractors using the Last Planner System: a case study on a gas subcontractor in repetitive housing projects Anales de Edificación last planner system; subcontractor management; gas facilities management; continuous improvement |
title | Collaborative planning of subcontractors using the Last Planner System: a case study on a gas subcontractor in repetitive housing projects |
title_full | Collaborative planning of subcontractors using the Last Planner System: a case study on a gas subcontractor in repetitive housing projects |
title_fullStr | Collaborative planning of subcontractors using the Last Planner System: a case study on a gas subcontractor in repetitive housing projects |
title_full_unstemmed | Collaborative planning of subcontractors using the Last Planner System: a case study on a gas subcontractor in repetitive housing projects |
title_short | Collaborative planning of subcontractors using the Last Planner System: a case study on a gas subcontractor in repetitive housing projects |
title_sort | collaborative planning of subcontractors using the last planner system a case study on a gas subcontractor in repetitive housing projects |
topic | last planner system; subcontractor management; gas facilities management; continuous improvement |
url | https://polired.upm.es/index.php/anales_de_edificacion/article/view/5306 |
work_keys_str_mv | AT xavierbrioso collaborativeplanningofsubcontractorsusingthelastplannersystemacasestudyonagassubcontractorinrepetitivehousingprojects AT karladelgadomartinez collaborativeplanningofsubcontractorsusingthelastplannersystemacasestudyonagassubcontractorinrepetitivehousingprojects AT luisbravosalomon collaborativeplanningofsubcontractorsusingthelastplannersystemacasestudyonagassubcontractorinrepetitivehousingprojects |